San Francisco’s Municipal Transportation Agency will be forced to redo part of a $52 million tunnel project because of a decision during construction two years ago that has led to potential stability problems along tracks used by several Muni light-rail lines.
Fixing the track work on the Twin Peaks Tunnel — a high-profile project marked by a series of difficulties, including the death of a worker struck by a falling beam — could cost tens of millions of dollars.
SFMTA officials first disclosed the issue last month to the agency’s board. The potential cost was first discussed publicly Tuesday during an SFMTA presentation to the San Francisco County Transportation Authority board.
The tunnel project included seismic retrofitting of the 2-mile-long structure, which first opened in 1918, and replacement of its 50-year-old track structure, including rails, ties and the ballast rock that provides a stable rail bed and allows water to drain from the trackway.
Julie Kirschbaum, the SFMTA’s director of transit, told the Transportation Authority board, a body made up of all 11 members of the Board of Supervisors, that instead of replacing the ballast rock during the project, as specified in the project contract, “a decision was made” to reuse the ballast that had been in place for decades.
“If the ballast had been cleaned and kind of shaken out so that all of the mud and fine particles were removed, reusing the ballast probably would have been a cost-effective and time-effective strategy,” Kirschbaum said. “But it wasn’t. And as a result, we now have ballast that is really more mud than rock and needs to be addressed.”
In an answer to a question from Supervisor Rafael Mandelman, Kirschbaum said the cost of having a contractor go in and replace the ballast would be in the millions of dollars.
“Millions or tens of millions?” Mandelman asked.
“I think tens of millions,” Kirschbaum said.
